As of May, Adhi Karya Light Rail Transit Construction 85% in Progress


PT Adhi Karya (Persero) Tbk stated that the construction progress of the Jabodebek light rail transit (LRT) phase I had reached 84.76% as of May 2021.

"As of May, the progress has reached 84.76 percent and relative to all cross-service achievements, the only thing left is finishing," said Corporate Secretary Adhi Karya Farid Budiyanto, Friday (4/6).

Details of the construction progress of each service line, including the construction progress of the Cawang-Cibubur I cross-service, have reached 93.81%. Then the Cawang-Kuningan-Dukuh Atas II cross-service construction progress has come 84.29%. Then the Cawang-East Bekasi line III cross-service progress has reached around 90.94%.

This progress includes, among others, track connection work and the physical construction of stations. Also, facilities in the form of trains have now parked along service line I, with 25 trainsets.

Later, all these trains will have their own parking space loca


Penulis : Widya